Connections

The connection process consists of the following steps:

  • Applying for technical terms
  • Ordering design on the basis of the technical terms
  • Submitting the design to the water company for approval
  • Concluding the connection contract
  • Construction of network according to the connection contract and approved design.

Find more information on the connection process HERE.

Single connection – a registered immovable does not have a water and/or sewer connection or you wish to reconstruct the existing connections.

A single connection process is started in case the registered immovable is located in an area with the existing public water supply and sewerage network on the street and:
• the registered immovable’s owner is willing to connect the property to the public water supply and/or sewerage system (PWSSS) for the first time, and it does not qualify as a subsidy connection;
• the registered immovable’s owner is planning to renovate (reconstruct) the building, which has been connected to the public water supply and/or sewerage system:
• the registered immovable’s owner intends to build an extension or make alterations;
• the owner of a registered immovable connected to the PWSSS wishes to use extra services of water supply or disposal of wastewater and storm water and drainage water or other soil- or surface water or use such services to the extent, which requires an extension or alteration of the PWSSS.